The Juice - Oct. 26

Work to begin as early as next week
##SENDGRIDOPENTRACKING##

Oct. 26, 2021

Centennial-Vollmer Halls Renovation Project updatease Kapers audition

Since the summer of 2020, the College has been quietly raising money to fund the renovation of Centennial and Vollmer halls with a focus on inclusion and belonging. These residence halls, which house about half of the first-year class, have remained nearly the same since their construction in the early to mid-1950s. With fundraising for the estimated $11 million project nearing completion, the College has engaged Cardinal Construction to serve as the project manager and lead the bidding process for the work.

 

Project highlights

A small addition in the northeast corner where Centennial and Vollmer connect will include an elevator, accessible walkway connecting the halls’ first floors, and a second-floor addition with a kitchen/lounge space and study rooms.
New heating system
Air conditioning throughout the buildings
Updated bathrooms
Updated laundry rooms on each floor
Accessible single rooms with their own bathrooms
Updated and accessible common areas

 

Project funding

The project is expected to cost about $11 million. The College has raised $6 million in donor gifts and secured a $1.5 million challenge grant that, when completed, will bring the total raised to $9 million. The Board of Regents has directed the College to fulfill the challenge by June 1, 2022. The College also is applying for a $2 million State Historical Tax Credit that will bring the total secured for the project to the needed $11 million.

 

Project timeline

Dependent on final approval of the construction contract by the Board of Regents, this project will be completed in three phases, with work beginning in November 2021 and ending in August 2023.

Phase 1 – Addition (including areas in Centennial & Vollmer connected to the addition)
Begin groundwork in November 2021
Begin other work in December 2021
Finish work in early August 2022
Phase 2 – Remodel Vollmer Hall
Begin work in late April 2022 – To do this, some students living in Vollmer at the end of Winter Term 2022 will need to be relocated to other rooms on campus. More details will be shared with those students as the plans are finalized.
Finish work in mid-August 2022
Phase 3 – Remodel Centennial
Begin work in late April 2023
Finish work in mid-August 2023

 

If you have questions about this project, please visit www.warburg.edu/cent-voll or contact Scott Sharar.

 

 
JUICE GUIDELINES
ABOUT THIS EMAIL
The Juice is a weekly e-newsletter sent Mondays and other times as needed to communicate campus news and events. Most items will run twice, then continue to be available in the Information Center.
TO SUBMIT AN ITEM

The deadline for submissions each week is 4 p.m. Thursday. Send items to juice@wartburg.edu. Please keep your submitted item short—no longer than one paragraph—and let us know if your item is for students, faculty/staff, or both audiences. Direct questions to Stephanie Boeding, editor and email marketing manager for Marketing & Communication, at ext. 8760 or via email. If you have an item that must run immediately, please contact the editor directly.

Wartburg College

100 Wartburg Blvd.

Waverly

Iowa

Unsubscribe

Wartburg students, faculty and staff: Please note The Juice is an official communication of the college, and per your connection with the institution, you must allow your inbox to receive college communications at your college-provided email account. Those who unsubscribe will be charged a fee for restoring your email preferences.

 